NI Water Planned Work in Ballyclare

04 July 2016

 

Northern Ireland Water are to install a storm sewer for a new housing development on the Ballynure Road as per the drawing above.

The contractor will carry out preliminary works, which involves a lane closure on the Ballynure Road from Monday 4 July to Friday 8 July.  These works are a prelude to the full closure of the Ballynure Road from Monday 25 July for a period of up to 6 weeks.

The laying of the storm sewer will start at the carpark of Lidl and head towards the proposed new housing development (outlined in red).  This will result in a detour around the A57 Templepatrick Road for a period of time for anyone coming to Sixmile Leisure Centre from the Town Centre.

Once the storm sewer is laid past the entrance to Sixmile Leisure Centre, that section of the Ballynure Road will be reopened but anyone travelling to the Leisure Centre from the top end of the Ballynure Road, will be detoured around the A57.

For more information on these planned works please contact 028 9034 0078.